Berth 200 Rail Yard

Herzog is the prime contractor undertaking the earthwork and track construction for this project. We relocated the existing Pier A railroad switching and classification yard to expand the rail yard facility in the 28 acre site. The scope of work included demolition of existing infrastructure, site preparation, and construction of the railroad switching and classification yard. Main project components included railroad track, railroad signalization, buildings, and site improvements. The track construction encompasses over 58,000 new track feet. We installed a Centralized Train Control (CTC) signals for mainline track improvements and grade crossing signal protection for five at-grade street crossings.

  • Location: Los Angeles, California
  • Owner: Port of Los Angeles
  • Cost: $89 million
  • Completion: 2014
  • System Type: Freight Rail

 