Lifted Logic Web Design in Kansas City clock location phone play check_box_outline_blank check_box chevron-down chevron-left chevron-right chevron-up facebook instagram linkedin google plus pinterest radio_button_checked radio_button_unchecked x arrow-up send globe marker close controls Spotify applepodcasts

POLA Berth 200 Rail Yard Project

Los Angeles, CA

Client

Port of Los Angeles (POLA)

Delivery Method

Bid-Build

Division

HCC

Capability
Rail Construction

Construction

Details

Year Started
2012
Year Completed
2014
Project Elements
  • Freight rail
  • Rail yard

Overview

This port expansion project provided a new 95-acre railroad switching and classification yard UP, BNSF, and Pacific Harbor Line (PHL) railroads. Project elements included removal of 6,000 ft of existing tracks, demolition of existing facilities and 28-acres of paved surface area, importation of 90,000 cy of fill material, 60,000 ft of wood tie ballasted track, 6,500 ft of concrete tie track, 1,500 ft of embedded track, 60 turnouts, relocation of active petroleum, fuel, and high-pressure gas pipelines, a new water distribution system, and installation of a photovoltaic solar panel system, 20,000 tons of asphalt, an 8,200 sf two-track locomotive maintenance and fueling facility, an 8,100 sf yard administrative building for PHL, and site-wide lighting and fencing.

+
CSX Intermodal Fairburn Capacity Expansion
Division

HCC

Capability
Rail Construction
+
Middle Harbor – Pier E Terminal Container Yard/Intermodal Railyard, Phase 1
Division

HCC

Capability
Rail Construction
+
Pier 400 Corridor Storage Tracks Expansion
Division

HCC

Capability
Rail Construction